Project Information

As work on the North Bay Regional Health Centre Project continues, check this page regularly for information on the latest developments at the site.

Project Data

Building Area: 725,000 ft²
Foundations: 2,375 steel piles (130,000 linear ft)
Concrete structure: 33,000 m> of concrete
Structural steel: 1,600 metric tonnes
Timber structure:
 
120,000 board ft. decking
550,000 board ft. glue lam
Hospital Equipment: 15,000 pieces to relocate or purchase
Mechanical systems:
 
 
29 air handling units - total output 295,000 litres of air/second allowing for total building air exchange of fresh air every hour!
Leadership in Energy &
Environmental Design (LEED):
 
Certified

Substantial completion was achieved on June 14, 2010. This means over 99% of the construction is complete.
Final completion will occur on July 29, 2010.

Project Milestones

     
Mobilize March 2007  
Concrete structure: April 2007  
Rough-Ins November 2007  
Structural Steel December 2007  
Timber Structure February 2008  
Substantial Completion June 2010  
Final Completion August 2010  
Patient Care Begins January 30, 2011